Finland Orders Preparatory Work Suspended at Two Google Data Center Sites

The LVV authority has ordered work that significantly alters the environment to stop in Muhos and Kajaani until environmental impact assessments are completed. Tuike Finland must explain how it will proceed; the order is not a final ruling on possible violations.

A red stop sign shaped like a raised hand stands in front of a concrete block and rubble; beside it, a small conifer and rocks sit beneath a glass dome.
AI-generated conceptual illustration · Edition Business

Finland’s Licensing and Supervisory Authority (LVV) ordered Tuike Finland, the company representing Google in the country, to suspend preparatory work that could significantly alter the environment at the Muhos and Kajaani sites. The suspension must take effect immediately and, in any event, be implemented before October 23, 2026. The measure will remain in force until the relevant environmental impact assessments are completed.

The order comes as the LVV examines whether work on both projects began before the required assessments were completed. According to the authority, the work carried out includes tree clearing, removal of topsoil, construction of roads and storage areas, and alteration of ditches.

The LVV requests an explanation and warns of possible enforcement measures

Tuike Finland must submit an explanation by October 14 and detail how it intends to proceed. The LVV said it could initiate enforcement proceedings if the company does not comply with the order; EFE’s coverage reported that the authority warned of a possible fine.

The suspension is an administrative measure to halt preparatory work while the environmental assessment is completed. It is not a final ruling on whether a violation occurred and does not, by itself, determine the outcome of the review. The company may submit its explanations, and the authority will have to assess the information available.

Tommi Muilu, head of the LVV’s Environment Department, argued that large-scale work can undermine the preventive effectiveness of the assessment by making it harder to analyze alternatives and prevent environmental damage. The purpose of the process, he explained, is to identify and assess impacts before construction progresses.

Google acknowledges that it did not meet its own standards

Google spokesperson Sondre Ronander said the company understands the concerns and that, in this case, “we have not lived up to our own standards.” He added that it would review the LVV’s conclusions and follow its instructions.

Google also said it acted in good faith, conducted nature surveys, and took measures to protect areas of value. As part of its landscaping and biodiversity plans, Ronander mentioned the planting of trees across 130 hectares in Muhos. This initiative announced by the company does not replace the outstanding environmental assessments or change the terms of the order.

Finland’s Minister of Environment and Climate, Sari Multala, called the matter serious and said the projects would likely be delayed because of the problems with the assessments. This is the minister’s forecast, not a definitive schedule for the work that has been announced.

The context of investment in Finland

The two sites are part of Google’s plans to expand its data center infrastructure in Finland. In September, the company announced an investment of 13 billion euros over the next two years, for digital infrastructure and its operations related to artificial intelligence. The LVV’s order concerns preparatory work in Muhos and Kajaani; the available information does not indicate that it suspends other projects or the entire announced investment.

For companies developing infrastructure in Finland, the case highlights the importance of completing applicable environmental assessments before starting work that could substantially change the environment. The specific scope of the obligations depends on each project and on the decisions of the competent authorities; the current order alone does not make it possible to determine Tuike Finland’s final responsibilities.

Sources and methodology

  1. Finlandia frena 2 centros de datos de Google tras la tala de ... ↗es.euronews.com
  2. Finlandia ordena a Google detener las talas ilegales en ... ↗www.swissinfo.ch
  3. Google told to halt work on datacentres in Finland over environmental concerns ↗theguardian.com
Editorial methodology →Corrections
Report an error ↗

Continue exploring

Conceptual illustration of a marble approval stamp connected by a wooden bridge to a telecommunications tower on a metal base.
News · 14.10.2026

CNA Authorizes the Sale of Movistar Mexico to OXIO for $450 Million

Mexico’s National Antimonopoly Commission (CNA) approved the sale of Telefónica’s business in the country to Melisa Acquisition, a consortium led by OXIO. The transaction, valued at **$450 million**, clears a key regulatory hurdle, although final closing still depends on pending procedures and legal deadlines.

Read story
Scale model of a luxury electric car on a stone pedestal, next to a marble charger and a key.
News · 14.10.2026

Jaguar targets North America as key market for the Type 01

Jaguar Land Rover has positioned **the United States** as the priority market for the launch of the **Type 01**, its new four-door electric grand tourer, following the positive reception of the prototype in **Canada** and the US market itself. With a starting price of **£130,000** (approx. €153,000) and a power output of **1,030 hp**, the brand aims to attract a new generation of luxury buyers, betting on design and exclusivity amid the uncertainty of electric vehicle demand in the region.

Read story